Project Details
● Installation



These are the equipment needed for today's installation. As it is an explosion-proof construction, you can see a lot of explosion-proof products such as explosion-proof junction boxes and explosion-proof flexibles.



To install Fix 800, you must first fix the bracket. Use a knife block to position it.








Proceed the same way for all other installation points.



All installation points use explosion-proof flexible cables to organize wires.


The junction box was also installed using an explosion-proof junction box.







Work began on the outside of the storage room in response to a request to connect the power supply to the explosion-proof control box. However, since it is an explosion-proof facility, drilling must be done to insert an additional power supply, but since the equipment is connected at the bottom and the control box is thick, it was more difficult than expected and a lot of time was spent drilling the explosion-proof control box.



Among the installation points, the inside of the waste storage room was ventilated, but an odor similar to YuxMagic was generated, so installation work was carried out with periodic breaks.■ Installation completed - Waste storage room installation completed.



- Waste storage room installation completed


- Completed installation of waste storage room outside




All five points were installed without any problems. Installation was completed after product demonstration and product training by injecting prepared test gas. In a gas measuring environment, when you do not know the gas generated, or when you know the gas generated but cannot confirm the exact concentration, it is difficult to make a choice before purchasing. The way to safety is to purchase a gas meter with an accurate measurement range by considering everything such as environmental factors, generated gas, frequency, and concentration through sufficient consultation with experts. At RS Korea, we In addition to simple product sales, we are a gas specialized company that provides self-calibration/domestic repair (A/S)/production/delivery/installation work. We provide 1:1 customized solutions for gas measurement environments based on our experience conducting demonstration / inspection / delivery / repair / installation work in various environments.


RS Korea Repair and Inventory Room Today's blog Organizing environment: Designated waste recycling facility and energy production facility company Product: Gas measuring gas Gas and measuring range: LEL (combustible gas) 0-100%lel Installation number of people and time: 4 people, 8 hours required Other information: All lines are organized with explosion-proof flexible. Since all items on site are explosion-proof equipment, drilling takes several hours. The volatile smell at the site is strong, so take periodic breaks. This concludes the blog on the explosion-proof installation of waste recycling facility gas meters. In addition, if you have any inquiries about installation, test operation, on-site repairs, or other environmental measuring instruments, please contact the number below. ☎ 031-340-6952


This was RS Korea. Thank you.